Eyeing completion by February 2027: MMRDA speeds up work on Atal Setu–Mumbai-Pune Expressway connector
✨ AI Summary
🔊 جاري الاستماع
The foundation work has been completed at 143 of the 176 locations, while piers have been constructed at 141 sites, with 88 already fitted with pier caps, officials said.